2017 Roadway Projects
Kings Canyon:
Construction Status: Land owner (Loren Carlson) has asked for added work to be completed to remove a rock near approach that could be affecting culvert hydraulically. Jon Beckett has equipment in the area and told land owner he would perform the work and would take 15 minutes.
- Estimated Completion: Summer 2017
- Construction Cost: No added cost
Loveland Heights:
Construction Status: All grading and pipe installation efforts are complete at this time. Contractor put off paving until Summer 2017. A bid to perform the paving has been requested for and has yet to be submitted by the contractor.
- Estimated Completion: Summer 2017
- Construction Cost: $37,921.50 w/o paving
Boogie Woogie Way:
Construction Status: Work substantially complete. Additional work requested by land owner to address fore slopes along existing drainage ditch just north of CR 44H.
- Estimated Completion: Summer 2017
- Construction Cost – Unknown
Spencer Mountain Road:
Construction Status: Construction work commenced week of 6/19
- Estimated Completion: Middle July 2017
- Construction Bid Cost – $228,488.00 (Project is expected to over-run with added 2,000’ of roadway onto the end of the project, requested added cost from contractor)
Paradise Park Road:
Construction Status: Contract awarded to Custom Design Fabricators (Pre-construction Meeting held 5/31)
- Estimated Completion: Beginning August 2017
- Construction Bid Cost: $141,734.50 (Project is expected to over-run with added culvert removal and replacement, requested added cost from contractor)
Rist Creek Road:
Construction Status: Construction underway with project currently approximately 50% complete
- Estimates Completion: End of June 2017
- Construction Bid Cost – $187,380.50
Patience Way:
Construction Status: Contract awarded to Road Runner Grading
- Estimated Completion: End of July 2017
- Construction Bid Cost: $45,400.00
256 George Stadler Road (Dykstra):
Construction Status: Contract awarded to Custom Design Fabricators (Pre-construction Meeting held 5/31)
- Estimated Completion: Beginning of July 2017
- Construction Bid Cost: $31,989.25
- 2017 Crossing Projects
Cedar Brook:
Construction Status: Contract awarded to Road Runner Grading
- Estimated Completion: End of August 2017
- Construction Bid Cost: $171,131.00
Glen Haven:
Construction Status: Construction approximately 75% complete
- Estimated Completion: End of June 2017
- Construction Bid Cost: $317,711.00
Pine Valley:
Construction Status: Project Awarded to Coal Creek Excavation (Pre-Construction Meeting held 5/22)
- Estimated Completion: End of July 2017
- Construction Bid Cost: $178,480.00
9469 Rist Canyon (Levick):
Construction Status: Project currently under construction with installation of culvert to commence week of 6/19
- Estimated Completion: Middle of July 2017
- Construction Bid Cost: $79,380.00
10548 CR 43 (Mccallum):
Design Status: Working through final design and bid documents
- Estimated Completion: Fall 2017
- Estimated Construction Cost: $414,000.00
10518 CR 43 (Pat Karspeck):
Design Status: Working through final design, bid documents, and access and construction easement documents
- Estimated Completion: Fall 2017
- Estimated Construction Cost: $375,000.00
12444 CR 43 (Mary Allen):
Design Status: Working through final design bid documents, and access and construction easement documents
- Estimated Completion: Fall 2017
- Estimated Construction Cost – $365,000.00
13500 CR 25E (Friede):
Design Status – Working through preliminary design and hydraulic evaluations
- Estimated Completion: Fall 2017
- Estimated Construction Cost – $200,000.00