2017 Roadway Projects Kings Canyon: Construction Status: Land owner (Loren Carlson) has asked for added work to be completed to remove a rock near approach

2017 Roadway Projects


Kings Canyon:

Construction Status: Land owner (Loren Carlson) has asked for added work to be completed to remove a rock near approach that could be affecting culvert hydraulically. Jon Beckett has equipment in the area and told land owner he would perform the work and would take 15 minutes.

  • Estimated Completion: Summer 2017
  • Construction Cost: No added cost

Loveland Heights:

Construction Status: All grading and pipe installation efforts are complete at this time. Contractor put off paving until Summer 2017. A bid to perform the paving has been requested for and has yet to be submitted by the contractor.

  • Estimated Completion: Summer 2017
  • Construction Cost: $37,921.50 w/o paving

Boogie Woogie Way:

Construction Status: Work substantially complete. Additional work requested by land owner to address fore slopes along existing drainage ditch just north of CR 44H.

  • Estimated Completion: Summer 2017
  • Construction Cost – Unknown

Spencer Mountain Road:

Construction Status: Construction work commenced week of 6/19

  • Estimated Completion: Middle July 2017
  • Construction Bid Cost – $228,488.00 (Project is expected to over-run with added 2,000’ of roadway onto the end of the project, requested added cost from contractor)

Paradise Park Road:

Construction Status: Contract awarded to Custom Design Fabricators (Pre-construction Meeting held 5/31)

  • Estimated Completion: Beginning August 2017
  • Construction Bid Cost: $141,734.50 (Project is expected to over-run with added culvert removal and replacement, requested added cost from contractor)

Rist Creek Road:

Construction Status: Construction underway with project currently approximately 50% complete

  • Estimates Completion: End of June 2017
  • Construction Bid Cost – $187,380.50

Patience Way:

Construction Status: Contract awarded to Road Runner Grading

  • Estimated Completion: End of July 2017
  • Construction Bid Cost: $45,400.00

256 George Stadler Road (Dykstra):

Construction Status: Contract awarded to Custom Design Fabricators (Pre-construction Meeting held 5/31)

  • Estimated Completion: Beginning of July 2017
  • Construction Bid Cost: $31,989.25
  •  2017 Crossing Projects

Cedar Brook:  

Construction Status: Contract awarded to Road Runner Grading

  • Estimated Completion: End of August 2017
  • Construction Bid Cost: $171,131.00

Glen Haven:

Construction Status: Construction approximately 75% complete

  • Estimated Completion: End of June 2017
  • Construction Bid Cost: $317,711.00

Pine Valley:

Construction Status: Project Awarded to Coal Creek Excavation (Pre-Construction Meeting held 5/22)

  • Estimated Completion: End of July 2017
  • Construction Bid Cost: $178,480.00

9469 Rist Canyon (Levick):

Construction Status: Project currently under construction with installation of culvert to commence week of 6/19

  • Estimated Completion: Middle of July 2017
  • Construction Bid Cost: $79,380.00

10548 CR 43 (Mccallum):

Design Status: Working through final design and bid documents

  • Estimated Completion: Fall 2017
  • Estimated Construction Cost: $414,000.00

10518 CR 43 (Pat Karspeck):

Design Status: Working through final design, bid documents, and access and construction easement documents

  • Estimated Completion: Fall 2017
  • Estimated Construction Cost: $375,000.00

12444 CR 43 (Mary Allen):

Design Status: Working through final design bid documents, and access and construction easement documents

  • Estimated Completion: Fall 2017
  • Estimated Construction Cost – $365,000.00

13500 CR 25E (Friede):

Design Status – Working through preliminary design and hydraulic evaluations

  • Estimated Completion: Fall 2017
  • Estimated Construction Cost – $200,000.00